ABS Payroll TIPS & TRICKS
Structuring of Projects & jobs
Here are a few ways to structure your Projects and the jobs that you create.
- Sample 1 is simply batching all employees on a per week basis
- Sample 2 is batching by department.
- Sample 3 is batching it further down, into departments. This is if you want to focus on processing each department at a time.
- Sample 4 is batching it by background days.
Tip: In all above scenarios, you will not be able to process/complete your payroll until all timecards are submitted and approved, so 1 person could tentatively hold up 30 others waiting to be paid.
SAMPLE 1 |
|
SAMPLE 2 |
|
|
SAMPLE 3 |
|
SAMPLE 4 |
|
|
|
All employees |
Split by Crew/Actors/BG |
|
Split by Dept |
|
Background days (daily) |
|
Production Company |
Production Company |
|
Production Company |
|
Production Company |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Project Name |
|
Project Name |
|
|
Project Name |
|
|
Project Name |
|
|
Job Week 1 |
|
|
Crew Week 1 |
|
|
Directing Team Week 1 |
|
|
Background Day 1 |
|
|
Job Week 2 |
|
|
Actors Week 1 |
|
|
Camera Week 1 |
|
|
|
Employee #1 |
|
|
Job Week 3 |
|
|
Background Week 1 |
|
|
Grip Week 1 |
|
|
|
|
Employee #2 |
|
|
Job Week 4 |
|
|
|
|
|
|
Electrical Week 1 |
|
|
|
Employee #3 |
|
|
|
|
|
Crew Week 2 |
|
|
Construction Week 1 |
|
|
|
Employee #4 |
|
Project Name |
|
|
Actors Week 2 |
|
|
etc |
|
|
|
|
Employee #5 |
|
|
Job Week 1 |
|
|
Background Week 2 |
|
|
|
|
|
|
|
Employee #6 |
|
|
Job Week 2 |
|
|
|
|
|
|
Directing Team Week 2 |
|
|
Background Day 2 |
|
|
Job Week 3 |
|
|
Crew Week 3 |
|
|
Camera Week 2 |
|
|
|
Employee #1 |
|
|
Job Week 4 |
|
|
Actors Week 3 |
|
|
Grip Week 2 |
|
|
|
|
Employee #2 |
|
|
|
|
|
Background Week 3 |
|
|
Electrical Week 2 |
|
|
Background Day 3 |
|
|
|
|
|
|
|
|
|
Construction Week 2 |
|
|
|
Employee #1 |
|
|
|
|
|
|
|
|
|
etc |
|
|
|
|
Employee #2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Entertainment Industry
ABS:PMTS ™ system is built to track based on actual hours worked. Traditionally in the production realm, production will utilize a “guaranteed” number of hours per day. The standard guarantee hours are usually a 10-hour day, or a 12-hour day. We will use a 10-hour day below, as our example.
The system is smart enough to back out lunches, but it is not paying attention to the guaranteed number of hours or the meal break that is potentially a paid lunch. This is what makes the entertainment industry unique, and payroll rules unique. So, there are two ways to go about scheduling your crew hours.
Option #1:
Schedule a 10-hour day, with an additional 30min-1 hour, if it’s going to be a paid lunch.
Option #2:
Schedule 10-hour days, and don’t include or worry about lunch times. So only worry about the top row. You would slot in 8am and a 6pm end. You would ZERO out the In/Out 2 boxes (bottom boxes set to blank).
So your timecard schedule would read like this